20 Aug 2026
Refinery modernisation is rarely one project. It is four parallel workstreams — process equipment, piping and valve replacement, power supply, and automation — executed on a plant that has to keep running between turnarounds. Refinery modernisation supply is therefore judged less on unit price than on whether the material arrives certified, traceable and in the sequence the construction programme needs. This article explains what each workstream involves, why traceability and standards compliance dominate refinery procurement, how pipeline and valve specifications are set for refinery service, what a SCADA installation changes operationally, and how an operator should scope such a project — illustrated with work IB Group has carried out at refinery and petrochemical plants in Azerbaijan and Kazakhstan.
Operators usually reach for modernisation for one of four reasons: a product specification has tightened, an ageing unit has become a reliability risk, energy cost per tonne has drifted too high, or the control system can no longer give the operating team the visibility it needs. Each reason pulls in a different workstream, and most real programmes combine several.
| Workstream | Typical scope | Dominant procurement issue |
|---|---|---|
| Process equipment | New or upgraded units — treating, separation, heat exchange | Long-lead items set the critical path for everything else |
| Piping and valves | Replacement of corroded or under-rated lines, block and control valves, tie-ins | Material certification and matching existing line specifications |
| Power supply | Substations, distribution, backup generation, electrical equipment | Availability during the tie-in and compliance with grid requirements |
| Automation and SCADA | Instrumentation, control and data acquisition, operator interfaces | Integration with running units and the plant's existing control philosophy |
The four projects referenced throughout this article map onto those workstreams: the diesel fuel hydrodesulfurization system in Aksay, Kazakhstan on process equipment, the pipeline and valve supply for the Heydar Aliyev Oil Refinery on piping, the substation in Aksay on power, and the SCADA installation at the Pavlodar Oil Chemistry Refinery on automation.
Where modernisation is driven by fuel quality, the unit itself is the project. The Aksay hydrodesulfurization system, built near the Karachaganak gas-condensate field in the West Kazakhstan Region, was implemented to improve fuel quality, minimise environmental impact and meet ecological standards, with IB Group supplying modern technologies and equipment meeting international standards. Projects of this type are defined by the product specification the plant must reach; every downstream decision about piping, materials and instrumentation follows from it.
In most industries material certification is paperwork. In a refinery it is the product. A line carrying hot hydrocarbon under pressure is a safety case, and that case is built on documents proving that each pipe, valve and weld is what the design assumed.
Getting this wrong is expensive in a way that is easy to underestimate: material that arrives without the right certification is not a delay of days but a rejection, and on a turnaround the replacement has to be found inside a fixed shutdown window.
Refinery lines are specified from the process conditions outward. The medium, its temperature and pressure, and its corrosivity determine wall thickness and material grade; the service determines whether the connection is flanged for maintainability or welded for integrity; and the plant's existing line classes determine what the new material must match so that the tie-in works.
The valve side follows the same discipline. The Babcock valves in IB Group's range are specified for a maximum pressure of up to 100 bar (10 MPa) across −50 °C to +450 °C, with carbon steel and stainless steel bodies and flanged or welded connections — an envelope that covers oil and gas processing plants, high-pressure boiler systems, energy and heat-exchange processes, and chemical and heavy industrial operations. What matters in modernisation work is that valve and pipe are specified as one package, since welded ends require matching wall thickness and flanged ends require matching flange standards.
Two of the projects above are exactly this kind of package. At the Heydar Aliyev Oil Refinery, pipeline and valve supply was carried out to enhance energy efficiency, reduce operational costs and ensure maximum safety, with products supplied to modern standards to strengthen the resilience of the plant's infrastructure. In the "Azərkimya" Production Association pipeline renewal, IB Group acted as supplier of high-quality pipes meeting modern standards, in a project aimed at increasing the sustainability of the petrochemical industry, improving energy efficiency and reducing operational costs.
SCADA — Supervisory Control and Data Acquisition — is the layer that collects, processes and displays plant data in real time. Unlike a pipe replacement, its value is not visible in the field; it shows up in how the plant is run. At the Pavlodar Oil Chemistry Refinery in Pavlodar, Kazakhstan, IB Group participated in the SCADA installation, and the benefits are the ones that define this class of system:
For a refinery operator the practical consequence is that modernisation stops being a one-off event. Once the plant is instrumented, the data that justifies the next investment — which exchanger is fouling, where energy is leaving the process — is generated continuously rather than assembled by hand during the next audit.
New process units and new automation both add electrical load, and both stop being useful if supply is not in place when they are commissioned. Power scope covers distribution design, substation work, backup generation and the installation and maintenance of electrical equipment, and it has its own approval and connection timelines that rarely match the mechanical programme.
The Aksay substation project, near the Karachaganak gas-condensate field in the West Kazakhstan Region, is an example of this workstream standing alone: equipment meeting international standards was supplied for reliable, safe transmission of high-voltage electricity, with infrastructure designed to meet the energy needs of industrial facilities and the local population. Within a modernisation programme the same capability appears as power solutions — energy supply system design, generators and backup power, energy efficiency auditing, and the installation and maintenance of electrical equipment.
Refinery programmes fail at interfaces more often than at components. The usual fault lines are between supply and installation, between disciplines, and between the standards each party assumed. Three questions decide how the package should be written.
This is the ground covered by contract support services — drafting and reviewing contracts, negotiations, risk assessment, contract administration and change management — so that legal and technical detail stay aligned as the programme moves.
A scope that survives execution usually answers the following before enquiries go out:
If you are scoping refinery or petrochemical modernisation and want pipeline, valve or power scope reviewed against your conditions, contact the IB Group team and the available supply will be confirmed against your specification.
Refinery modernisation usually combines four workstreams: new or upgraded process equipment, replacement of piping and valves that are corroded or no longer rated for the duty, power supply work such as substations and backup generation, and automation including SCADA systems and instrumentation. Most programmes run on a live plant, so the sequence matters as much as the content — long-lead items and shutdown windows drive the schedule. The starting point is the reason for modernising: a tighter product specification, a reliability risk, energy cost, or insufficient operational visibility. Each driver leads to a different mix of scope.
Because refinery piping is part of a safety case, not just an asset. Heat numbers, mill certificates and marking prove that each delivered pipe and valve matches what the design assumed, and that documentation is what supports later integrity assessment and inspection. It also governs acceptance: material that arrives without the right certification is not a minor delay but a rejection, and during a turnaround the replacement must be found inside a fixed shutdown window. For that reason the standard framework, inspection regime and certificate list are agreed before manufacturing begins.
SCADA collects, processes and displays plant data in real time. At the Pavlodar Oil Chemistry Refinery in Kazakhstan, where IB Group participated in the SCADA installation, the benefits are those typical of the system class: process automation that reduces manual intervention and improves efficiency, data analysis that gives detailed insight into plant performance and better-founded decisions, energy management that optimises consumption, and safety and control aligned with high standards. Operationally, the lasting effect is that the data justifying the next investment is produced continuously rather than assembled manually.
Refinery lines are normally specified to one of three frameworks. IB Group's oil-gas and industrial pipelines are manufactured in compliance with international standards including API 5L, EN and GOST, and its oil-gas and industrial valves comply with API 6D, EN and GOST. The Babcock valves in the range are rated for up to 100 bar, stated as 10 MPa under GOST, across −50 °C to +450 °C, with carbon steel and stainless steel bodies and flanged or welded connections. Because plants in the region often mix GOST-era design with EN or API extensions, accepted equivalences should be documented at the enquiry stage.
Decide first who carries interface risk. Separating supply from installation lowers the headline price but transfers coordination risk to the operator, which only pays off when the operator has the capacity to manage it. Then define what compliance means in the contract itself — accepted standards, inspection regime and certificate list — rather than leaving it to correspondence. Finally, agree a variation mechanism before it is needed, since tie-ins routinely reveal site conditions that drawings do not show. Contract support and project management services exist to keep these terms aligned with the technical scope.

13 Sep 2026
What API 5CT actually covers, why threads sit in API 5B, where API 5L begins, how J55 to P110 grades read, how LTC, BTC, EUE and premium connectors differ, and what to require on delivery.

10 Sep 2026
What a fish plate in railway track does, how the double-headed section clamps a rail joint, 1R65 and 2R65 sizes and weights, EN versus GOST steel grades, and how to match a plate to your rail profile.

07 Sep 2026
Which valve family fits which duty, how pressure and temperature decide between carbon and stainless steel bodies, what API 6D, EN 12516, EN 593 and GOST 33259 govern, and the checklist to send with an enquiry.